Planning with shelf life expiration date in SNP

0 Kudos

Dear all

Is it possible in SNP to plan on batch shelf life data?

Example:

Requirement date 20.09.2013

Batch A: shelf life expiration date of 18.09.2013

Batch B: shelf life expiration date of 30.09.2013

Run SNP heuristics on demand of requirement date 20.09.2013. Batch B should only be taken into account for stock netting. Is this possible in SNP?

If not, can this only be possbile using PP/DS?

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Peter,

As per my knowledge this is not possible in SNP heuristics.  But as you said this is possible using PP shelf life heuristics.   The Planning applications in SNP doesnt consider shelf life except optimizer which considers shelf life in a restricted way. but you can leverage shelf life planning book to display the shelf life data in SNP. For more details i would ask you to read thru the notes

Note 579556 - Taking shelf life into account with SNP optimizer

Note 1072022 - Shelf life in SNP

http://help.sap.com/saphelp_scm70/helpdata/EN/46/1da416078b5a68e10000000a1553f7/frameset.htm

Rgds,

Kiru