on 08-30-2013 6:58 PM
Dear all
Is it possible in SNP to plan on batch shelf life data?
Example:
Requirement date 20.09.2013
Batch A: shelf life expiration date of 18.09.2013
Batch B: shelf life expiration date of 30.09.2013
Run SNP heuristics on demand of requirement date 20.09.2013. Batch B should only be taken into account for stock netting. Is this possible in SNP?
If not, can this only be possbile using PP/DS?
Hi Peter,
As per my knowledge this is not possible in SNP heuristics. But as you said this is possible using PP shelf life heuristics. The Planning applications in SNP doesnt consider shelf life except optimizer which considers shelf life in a restricted way. but you can leverage shelf life planning book to display the shelf life data in SNP. For more details i would ask you to read thru the notes
Note 579556 - Taking shelf life into account with SNP optimizer
Note 1072022 - Shelf life in SNP
http://help.sap.com/saphelp_scm70/helpdata/EN/46/1da416078b5a68e10000000a1553f7/frameset.htm
Rgds,
Kiru
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
12 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.