11-13-2013 8:37 PM
I need the phase confirmation to be sent for each phase confirmation when it is entered prior to the completion of the PI sheet.
I have the following process instructions (shown below) assigned to my control recipe destination and I am showing how it appears in the created/released process order. The fields to enter the phase confirmation appear in the PI Sheet for each phase. However, when I enter values in the fields and save the PI sheet, the process message is not created in CO54 and I do not receive any error. When I finish entering all values into the PI sheet and complete the PI sheet then the phase confirmation messages are also created and will process successfully. However, as previously stated I need the phase confirmation to be sent for each phase confirmation at the time the confirmation is entered which is prior to the completion of the PI sheet. It is as if the event to execute the confirmation PI instruction is not getting triggered until PI sheet completion. I have a modified PH_CON message which removes some of the activity fields since we are only posting time for one activity.
0010 PPPI_DATA_REQUEST_TYPE Simple Data Request
0020 PPPI_MESSAGE_CATEGORY PI_PHCON
0030 PPPI_OPERATION 0100
0050 PPPI_PHASE 0110
0060 PPPI_PHASE_RESOURCE RES-3010
0070 PPPI_AUTOMATIC_VALUE Event Time
0080 PPPI_AUTOMATIC_VALUE Event Date
0090 PPPI_PLANT_OF_RESOURCE 1000
0100 PPPI_PROCESS_ORDER 1000697
0160 PPPI_INPUT_REQUEST Activity 1 :
0170 PPPI_ACTIVITY_1 0.050
0180 PPPI_REQUESTED_VALUE PPPI_ACTIVITY_1
0190 PPPI_ACTIVITY_1_UNIT h
0195 PPPI_OUTPUT_TEXT Unit of Measure:
0200 PPPI_OUTPUT_CHARACTERISTIC PPPI_ACTIVITY_1_UNIT
0205 PPPI_INPUT_REQUEST Finished :
0210 PPPI_REQUESTED_VALUE PPPI_ACTIVITY_1_FINISHED
0462 PPPI_INPUT_GROUP ------------------------------
0500 PPPI_INPUT_REQUEST Yield to confirm:
0510 PPPI_REQUESTED_VALUE PPPI_YIELD_TO_CONFIRM
0520 PPPI_UNIT_OF_MEASURE lb
0530 PPPI_INPUT_REQUEST Scrap to confirm:
0540 PPPI_REQUESTED_VALUE PPPI_SCRAP_TO_CONFIRM
0550 PPPI_INPUT_REQUEST Confirmation status:
0560 PPPI_REQUESTED_VALUE PPPI_STATUS_CONFIRMED
Regards,
Sherry
11-22-2013 1:04 AM
Hi Sherry,
there are several recent OSS notes for this area of PI-sheet
and CO54, 397025, 139073 etc.
Without knowing more details and the release you are using, it will be hard to
determine what needs to be changed. Could you kindly open an OSS message on
component PP-PI-PMA.
Thanks and best regards
Petra