on 11-18-2013 10:30 AM
Hi All,
When a change of the milestones is made in UI, the POC (date and percentage) is not indicated in CN60 transaction. However when we change manually the POC (in CJ20N) in SAP, it appears in CN60. How can we update the log for milestones and POC in CN60N? For other fields the changes appear.
Best Regards,
Shahir Mirza
Hi,
Found the solution myself. The note for milestone log updation need to be implemented. This maintains the log in CN60 Tcode for milestone and POC data.
Regards,
Shahir