Dear Gurus,

Need a clue on work center activity is not getting in routing it was configured in all the respective configuration part but it is not poping in routing any flash lights urgently..

Thanks & Regards,

Madhu.G

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear Guru's,

Issue is not yet solved please let me know the error on this on urgent basis

Important thing is, Initially the was maintained with external processing control key and maintained cost element any clues on it please let me know on urgent basis....

Thanks & Regards,

Madhu.G

Former Member
0 Kudos

Dear Gurus,

Issue is because of date relationship with work-center cost center.

Issue is solved....

Regards,

Former Member
0 Kudos

Please provide screenshots of routing & work center to understand your issue clearly.

Answers (1)

Answers (1)

Former Member
0 Kudos

Please check if you have ticked Reference Indicator for the activities.

Former Member
0 Kudos

Dear Sonal,

This is not due to reference indicator. Issue is due to the Work center & Cost center and Routing creation date should be in same then the formulas will be generated.

Any ways thanks for your input

Issue is resolved...

Regards,

Madhu.G