on 11-28-2013 4:43 PM
Hi Experts,
Please advise on the below issue -
Client currently uses a basic costing sheet which has base as secondary cost element (43), Overhead rate % (D000) and the Credits post to a Cost center (XXXX)
The requirement is they would like to split the cost in the future to 2 cost centers instead (XXXX & YYYY), keeping the base and overhead rate the same. They would like to see the split based on the profit center maintained on the Material master
Please note - Currently, we do not use origin group / Overhead key / Overhead group functionality
I was thinking maintaining origin groups will help resolve this issue, so I tested by assigning Origin groups (OR1 & OR2) on the Finished goods Materials and assigned these origin groups in the Credit rows (Additional row of Credit for 2nd Origin group)
Now, Costing sheet looks like below -
Row Base OH rate Desc From To Credit
10 ZLR Base
20 ZOH1 Overhd 10 Z01 ( Has CE1 + OR1 + Cost center XXXX)
30 ZOH1 Overhd 10 Z02 ( Has CE1 + OR2 + Cost center YYYY)
When I ran the Overhead calculation using above for a single material, system posts double entries, meaning if $100 overhead is to be posted - system posts 100 to Cost center XXXX and another 100 to Cost center YYYY!
Appreciate your inputs on this issue
Thanks
Hi..
COOM0001 User Exits for Overhead Rates have three components.
-. EXIT_SAPLKASC_001 : Calculation base
-. EXIT_SAPLKASC_002 : Overhead rate
-. EXIT_SAPLKASC_003 : Credit
Each component have example. Your requirement can be applied to system
Using EXIT_SAPLKASC_003’s example.
The Following is part of SAP’s description related to EXIT_SAPLKASC_003.
Sample coding is stored in the LXKSCF03 program for the following situation:
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mujju,
Follow the experts directions to derive different cost centers in the credit using user exit: COOM0001.
Before that please make note of it: The concept of origin group applies to materials only and not for others
And please let all know, do you wish to give different cost centers credit on plant basis? If yes, in this case you can achieve this simply by creating different costing sheets plant wise and assign them in the valuation variant plant wise.
Regards...
Jose
Hi Mujju,
We have the similar situation and trying to use this user exit and change the value of the base cost. Our user exit stops picks up the values but our out put is not changed. Can you share details of your code I am not sure what we are missing in the code. (I am functional consultant, can only read the codeand not code myself).
Thanks and Regards
Pal.
Hello Ajay,
Can you please specify the exit again and elobrate on the logic to be written.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Use exit coom0001. You can write logic to derive cost center for credit based on PC
Br. Ajay M
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.