on 12-23-2013 8:10 PM
HI experts
I would like to know what is different between closed work order and completed on SAP PM Module.
regards
nasser
See this conversation:Completed is technical comptete (TECO) - the technician has done his/her work, closed is settled and done also from an accounting perspective (settlement)
PM Work Order TECO and CLSD
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.