Hi Guys,
I want to know, is any one has went through the upgrade situation of 2 SAP system on MCOD database.
we have BI ABAP and BI Java sharing same database (MCOD) on single host and plan to upgrade from 7.01 to 7.31.
As per SAP documentation we can not perform parallel updates in MCOD systems.
But can we start the execution of the steps in parallel till the pre-processing phase and execute the downtime phase unparallel keeping it in mind there will two separate SUM dir one for ABAP and other for JAVA. Also we use nZDM methodology.
Regards
Pravin
Pravin, what did you do at the end? I am in the same situation. Please let me know.
Regards
Andreas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Technically, it should be feasible. However, it is not recommended practice because 2 systems sharing same database and in case, you want to reset upgrade/restore database then it will impact both the system.
Thanks,
Sunny
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
23 | |
11 | |
9 | |
8 | |
5 | |
5 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.