Dear Gurus,

I activated the business function for split order and then, I created split order for both Parent and Child splits status profiles. But when I am trying to split the order in order change mode in CO02 it is not showing the SPLIT ORDER function (which is in deactivate mode).


What could be the reason on this and any procedures are there please give me a flash lights on this asap.


Thanks & Regards,

Madhu.G

Accepted Solutions (1)

Accepted Solutions (1)

former_member184666
Active Contributor
0 Kudos

Hi Madhu,

Read the below doc for more understanding.

Thanks & Regards,

Ramagiri

Answers (2)

Answers (2)

Former Member
0 Kudos

Dear Ramgiri Ji,

My system package is EHP 5  ECC 6.0 and please do let me know the procedure steps to do it.

Regards,

Madhu.G

former_member184666
Active Contributor
0 Kudos

Hi Madhu,

Step by step procedure to split the order against the operation is already listed in my earlier reply. Please go through the document, it is explained clearly with screen shots.

Data in the document is pertaining to ECC 6.0 EHP 4

Thanks & Regards,

Ramagiri

Former Member
0 Kudos

Dear Ramagiri,

I am asking on how to avoid the by-product  and sales order screens.

Not able to understand in that document. So pls let me know the procedure....

Regards,

Madhu.G

former_member184666
Active Contributor
0 Kudos

Hi Madhu,

Apply note 1625001. Once you apply this note system will not display by product and batch.

Regards,

Ramagiri

Former Member
0 Kudos

Dear Ramagiri,

This is applicable only for GPD industry  solution, ours is agricultural based company will be there any impacts.

I hope Grouping requirements (?), Pegging requirements (standard) & Distribution (?).

Will be more specific on this please..

Regards,

Madhu.G

Former Member
0 Kudos

Dear Ramagiri Ji,

Any flash lights on this please.....

Regards,

Madhu.G

former_member206498
Contributor
0 Kudos

Hi Madhu,

To split an order, you have to select the operation in which the split process will be carried out. Otherwise, the split function will be deactivated.

Regards,

Julian