Guys,
I need a hand on this.
I can’t update combined price in CK24.
I did CK11N – got $100
I planned CK74N – got $20
I did CK11 again – got $120
But when I go to CK24 I keep seeing only $100.
I think costing variant properly prepared and OKTZ also since during the second CK11N I see the good value with good cost component assignment.
I have to costing variants with 2 different costing types. One updates the standard price another price other than standard price. Neither works.
What am I missing?
Many thanks in advance
G
Hi Gergej
I can think of only one reason.
The cost component that manages this additive cost is not relevant for inventory valuation in OKTZ
Can you check this if it is marked as NOT RELEVANT for inventory valuation
Br. Ajay M
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
That was the thing, thanks Ajay.
Another stuff what bothers me that the second costing variant which is practically identical with the first one doesn't update. The difference between the two is that the first one has price update "Standard price", the second "Commercial price".
I tried the second one with also "Prices other than standard price".
I CK24 I clicked the "Other prices" icon, entered relevant data and checked "Commercial price 1" but there was no update at all. 0 materials were updated succesfully.
THX
G
Dear Gergej
Just a wild guess:
After CK74N when you did the CK11N. did you save that.
Also check the Cost component in which this additive cost is to be added that it covers fixed and variable both in 'Cost share', because if you give price in CK74N in the Price-fixed column than it is treated as the fixed cost.
you are very right that If BOSS is there then we can only give wild guesses. All concrete points he already mentions in his replies. But no harm in trying, Right Ajay Sir?
Regards
Rajneesh Saxena
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Another guess. Does this scenario pertain to stock transfer??? If yes, check if additive costs for stock transfer is allowed in the costing variant
Br. Ajay M
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Adding to Ajay's reply, Are you sure the addictive cost saved ?
You have to hit the save button twice in CK74n before it saves the addictive cost.
Thanks
Hrusikesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.