Dear Experts,
In Project Systems - My user wants to update cost forecasting amount for some wbs elements manually for every month in SAP.
Can I suggest CJ40 or is there any other t-code to update cost forecasting for some wbs elements and also provide the necessary config setps with reports.
Thanks,
Hi,
Using CJ40, you can do cost planning either overall or annual basis. For monthly basis, you should use CJR2 as above suggested.
Regards
Shishir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Well it depends upon your business that how many versions you want to carried out. But initially you don't need to maintain 12 version monthly wise. System use 000(Create automatically from creation of CO area) by default.
For Planned line items, you can check report CJI4/S_ALR_87100186.
Regards
Shishir
Hi...
1 version is perfect. CJI4 is the best line-item report to use for planning values...
Sometimes users find it difficult to pass values to cjr2 (if you campare it with cj40). Therefore if your users have to update a small number of project/wbs's then go with cj40. If not then cjr2 is perfect...
cheers
panagiotis
Hi...
your user can use CJ40 for cost planning and CJ42 for revenue planning per project or per wbs element.
CJR2 can be used for massive uploads of planning data to multiple wbs elements/ projects (but needs some customization from yoru side).
Hope it helps
Panagiotis
PS cji4 is a very efficient report for plan line items.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.