Discontinued Material_Dependent Requirements

Former Member
0 Kudos


Hi All,

Material A (Discontinued) has been replaced with B (follow up), was updated material master with effective date 14.03.2014 and BOM with ECM for both.

'A' has zero stock, Last material movement for 'A' was happened on 13.03.2014.Mat 'B' is in use and getting correct requirement's.

Crux is, I still see the dependent requirements for mat 'A', not sure what could be the reson. I understand, if take MRP run (MD02) for 'A'; requirements will surely disappear.

Can somebody please tell the reason, why A is still having futured dependent requirements on MD04?

Many Thanks.

Refgards,

Deepak

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member184666
Active Contributor
0 Kudos

Hi Deepak,

Go through the below document and revert if you have any further query.

Concept of Discontinuation Data - Material Master and BOM

Thanks & Regards,

Ramagiri

Former Member
0 Kudos

Hi All,

In referenec to above thread, I run MD02 for discontinued material A (no stock since 14/03/2014) and all existing dependent requirements got deleted which is obvious.

Can someone please tell, why the dependent requirements were existed for mat A?

Regards,

Deepak

Former Member
0 Kudos

Can someone please provide thought "why material still generating requirements which is already discontinued"?

Let me know if need any more information.

Regards,

Deepak Girme

0 Kudos

Hello Deepak,

This forum is for SAP Manufacturing Execution topics. Try to post your question in appropriate forum.

Here is a forum finder. http://scn.sap.com/docs/DOC-18971

SCN PP Space http://scn.sap.com/community/erp/manufacturing-pp/content

Regards,
Alex.