Hi Team

In some of of SvO planned cost is not updated,what could be the reason of not updated planned cost automatically.

kindly revert.

Br, Kiran Unde

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

What do you mean by SvO??

Suggest you not to use any abbreviations in forum.

former_member267531
Participant
0 Kudos

HI

I meant Service order.(SvO)

Br, Kiran Unde

Former Member
0 Kudos

There could be many reasons.

  1. If its internal activity, check the work center, cost center assigned in work center, activity type in service order & activity price maintained in KP26
  2. If its External activity, check whether you have maintained the price in External tab of operations details screen
  3. Check the Control Key settings whether "Cost" tick mark has been selected or not.
  4. Check the Costing variant assignment to your service order under Control tab of Service order