on 04-16-2014 11:51 AM
Hi,
We have a requirement to redesign the existing BPM scenarios PI 70 to PI731Java only (Eclipse).
So can you please help me by providing steps to redesign Integration process in ESR and iFlow (steps in ESR and Steps in iFlow)
how to create integration process (process integration scenario) in ESR.
how to develop iFlow for BPMscenarios. we have a option generate integration flow from process integration scenario right...for this first i have to create a process integration scenario in ESR right...so how to create it in ESR.
Best Regards,
prasanth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Akshay,
Thanks for the Links.
Can you please provide steps (with navigation) in NWDS to configure BPM sceanrio
i am bit confused, where to create integrated configuration that we will craeted in Repository in old versions and iFlow for Directory objects and how to link both in NWDS developments
Do we need to craete integrated configuration in ESR of NWDS and how to link iFlow of process composer to ESR:(
Regards,
Prasanth
Hi Prasanth,
I was involved in a similar process recently, and I followed this excellent guide from William Li that details how the PI objects have changed from the different versions, it also introduces the PI migration tool which might be of some benefit for your project (you can point the migration tool at your old PI stack and select which integration configurations you want to migrate over onto the new java PI stack)
For ccBPM you will need to remodel this in the new 7.31 BPM tooling, there is currently no migration tool for this.
Hope this helps a bit!
Jon
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Prasanth
If you are coming from PI 70 ABAP to Process Orchestration 7.31 then its very important to realise that PI 70 used ccBPM, but PO 7.31 uses BPM which are completely different toolsets. There is a lot of existing doco and how to guides in the Process Orchestration space and I'd particularly recommend reading William Li's blogs on this
Good luck!
Jocelyn
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Prasanth
If you are coming from PI 70 ABAP to Process Orchestration 7.31 then its very important to realise that PI 70 used ccBPM, but PO 7.31 uses BPM which are completely different toolsets. There is a lot of existing doco and how to guides in the Process Orchestration space and I'd particularly recommend reading William Li's blogs on this
Good luck!
Jocelyn
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
23 | |
11 | |
9 | |
8 | |
5 | |
5 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.