on 04-17-2014 6:23 AM
Hello,
I have an issue in PR, where planned delivery time is picked wrongly. PR is created through MRP.
In info record, the planned delivery time is 8, in vendor master record planned delivery time is 0, and no contract exists. But when PR is created automatically through MRP, planned delivery time is 10 in PR. How is this possible, from where else does planned delivery time flow?
There are 4 materials in PO, among which 3 materials have pl.del time as 1 and for the fourth the time is 10, because of which when delivery is created for PO using VL10B, 3 materials are planned in one delivery and the fourth material is planned in another. Split in delivery is occurring. Statistical delivery dates are the same for all the four materials.
Please help e regarding this issue.
Regards,
Krishna Bharadwaj.
Hi Krishna,
What is the planned delivery time of the material in the material master?
Also are you assigning the source of supply in the PR and have mentioned the Porg?
Regards
Vivek Singh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.