PLANNED AND ACTUAL COSTS IN A PLANT MAINTENANCE ORDER NOT CALCULATING

Former Member
0 Kudos

Goodmorning guys,

When creating a plant maintenance order,the actual and planned costs cannot be calculated

with or without materials.The following message displays when trying to calculate.

regards

Accepted Solutions (1)

Accepted Solutions (1)

peter_atkin
Active Contributor
0 Kudos

You need to create an activity rate for 2014 for cost centre 51260201 and activity type NAHG20.

This can be done via transaction KP26, but is usually performed by your Finance team.

PeteA

Former Member
0 Kudos

Hi Peter,

That was already done by our finance team,still it persists

regards

Former Member
0 Kudos

hi peter,

we realised that the activity rate for 2014 was created but some check boxes for the planned costs were not checked hence wasnt reflecting...thank you

zayminthet
Discoverer
0 Kudos

ok, i am Mr. Min from Coca-cola myanmar. position is SAP Business Process Lead or Super User

i have question.

could you kindly see below scanario .

i have to set up Activity rate in KP26 per cost center for 2016.

but i really don't know what is the activity rate( average fixed Price) in KP26.

as per my previous year experience, if we havn't set up the rate in KP26, we can't create PM work order . Please tell me why is important and how they work.

( we are using SAP ERP R/3 , repetative manufacturing .) my email is mtzay@coca-cola.com.mm

Answers (0)