Why Remordplan value in the report S_ALR_870130558 is zero?

Former Member
0 Kudos

DEAR ALL,

THE planned-overall is contributed by network activities. But the remordplan is zero. wby could be remorderplan equal to planned costs contributed by network activity?

Could i do more configure?

Accepted Solutions (0)

Answers (3)

Answers (3)

gerry_hodgins
Active Participant
0 Kudos

Hi Lynn

The "qualifiers" apportioned/appended are goverened by the status of the network/order and the customizing.

Read  note 668240 on the Remaing Order Plan can



sanjeevc
Active Contributor
0 Kudos

Hi Lynn,

it is so like you can use once controlling version in a once and this kind of entry to be save in that version.

if this is not the reason then check OPSV setting like ++ is there for 20 category?

Regards,
Sanjeev

Former Member
0 Kudos

Hi,

Is your remaining Ord Plan value is according to :


Rem Ord Plan = Planned - (Actual + Commitment)


Also read the thread:


http://scn.sap.com/message/7915684#7915684



Also run CJEN and check again


Regards

Shishir