I need to create and assign an activity type to a W B S element and enter the rate plan rate. This will be similar to KP26 wherein you enter Cost Center and activity type with a plan rate. Here instead of Cost Center, I need to enter WBS 1 and activity type with a plan rate say 10$
Then I confirm some actual hours against to an internal order number 700 say 5 hours with a settlement to a WBS 2 .
Therefore the entry will be
Dr. Internal Order number 700 50$ (5X10)
Cr. WBS 1 50$ (5X10)
I also have a actual debit or expenses booked against WBS 1 is 70$
It means after confirmation of above to an internal order,
Dr. Expenses 70$
Cr. Confirmation 50$
balance unabsorbed against WBS 1 is 20$
Now I want to use revaluation of internal order functionality
Now I expect to see another debit to internal order
Dr. Internal Order number 700 with 20$
Cr. WBS1 20$
Now I settle the internal order to WBS 2, which will be
Dr. WBS 2 70$
Cr. Internal order 70$
I like to know if the above scenario is possible in PS, like setting up of a T code similar to KP26,
If I want to use revaluation of internal order what is configuration can I do?
I first like to map activity type with WBS only. Please if I can do it.
Raja
Hello all
Please respond to my problem.
Thanks
Raja
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.