PIR not showing in Md04 after certain date

Former Member
0 Kudos

Hi

The PIR's are coming from LTP.

The PIR's which are created after 03/2015 are not showing in MD04

MRP run back ground with NETCH still why PIR's are not showing?

What settings I have to check..

Regards,

Srihari.M

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hi Srihari,

Please chek in  MS04 you will get all PIRs for planning scenario version, but in MD04 all active versions PIRs will be get displayed. Then go to MS32 check the planning period for PIR.

Also note in MS64 you can copy all PIRs to active version.

Regards,

R.Brahmankar

Former Member
0 Kudos

Hi Brahmankar,

The Planning horizon in OPPQ is 100days and in OMPD the planning horizon for active version is 400days.

So in Inactive version is the planning horizon will be 100days am I correct.

Regards,

srihari.M

rupesh_brahmankar3
Active Contributor
0 Kudos

Hi Srihari,

Did you check MS04?

Go to MS32 enter your planning scenario then on next screen you will have Planned independent Requirement  tab here you will get period for PIR for active and inactive version.

OMPD setting is for MD61/62 demand management to enter the demand/forecast. And Planning horizon in OPPQ is used to planned that demand by using MRP Processing key  NETPL.

Regards,

R.Brahmankar

Former Member
0 Kudos

Hi Brahmankar,

We are using characterstics planning so in MD62 for materials -characterstics -percentage planning was not maintained after 01/2015, After maintaining this issue was resolved.

Regards,

srihari

Answers (3)

Answers (3)

0 Kudos

Check PerInd: LT Lot Size in OMI4 is blank.

Anupam1143
Active Contributor
0 Kudos

Hi

Check the Planning horizon maintained in MRP plant parameters in OPPQ.Also check whether these are visible in MD61/MD62/MD63 or not.

Also check the Planning horizon maintained as defult values in T code OMPD as well.

I hope the LTP Planning period is maintianed properly.

Regards,

Anupam Sharma

Former Member
0 Kudos

Hi

The requirements are visible in Md63, Planning horizon is 100 days.MRP processing key is NETCH.

The requirements up to 03/2015 are appearing in MD04.If it is planning horizon issue from 08/2014 its should not appear.

Regards,

Srihari

former_member196530
Active Contributor
0 Kudos

Please check the following  :

1.If you have done splitting of the required qty during PIR creation . , please check in MD62  whether , you have un-checked the Active Version for some of them  .If those qty. are falling after 03/2015  , then it will not pop up in MD04

2.While creation of PIR , if the planning period is beyond planning horizon , it will flag you a message and requirement will not display in MD04 , then check the same in OMPD and compare with planning period.

Regards

JH


former_member185379
Active Participant
0 Kudos

Hi, Have you checked how many days are mentioned in Planning horizon? Thanks