on 04-22-2014 12:04 PM
Hello,
I have configured Project Systems Progress Analysis and I am able to see values in CNE5. In CNE5 I am able to extract graphs for each column (e.g BCWP,BCWS, SV, CI etc) through menu Goto -> Graphic -> Totals Curve, but the user requires a Cost Vs Time Earned Value Curve also known as the S-Curve. Is it possible to extract S-Curve,consisting of Schedule Var and Cost Var, in SAP Project Systems ?
If it is then kindly let me know the procedure
Thankyou
I have found two options
Option 1 :
Go to CNE5 report,
Then click on the description of WBS element or main WBS element. You will get Drill down report for Period Overview.
Go to graphics icons and choose Period D Down. There you will get display for S-Curve
Option 2:
Go to CN41, select PD or WBSE...Goto>period breakdown...it will take u to new screen where u will have Periods in LHS and Plan cost, Actual costs, Budget etc., in RHS...then click on any column say Actual cost then goto>Graphic>Period Breakdown....U will see period in x-axis and Actual cost in Y-axis.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thankyou Shishir, the 'correlation' button will give me one curve for each column. I need only one curve for Actual Cost and one for Planned Value.The Cost on one axis and Time on the other axis
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check 'Correlation' button in graphics option in CNE5 if it will fulfill your need.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.