on 04-22-2014 12:37 PM
Hi All,
We are working on an implementation where a project is automatically created in SAP PS from SAP PPM (cProject) when a project is released in SAP PPM.
There are two problems we are facing:-
We don't want to settle costs to Profitability segment bu instead Cost Center.
Any help/pointers/suggestions are welcome.
Additional info: We have maintained some values in "Maintenance View for cProjects CO Scenario" in the path IMG -> Integration with Other mySAP.com Components -> SAP Portfolio and Project Management -> Project Management -> Collaboration Projects -> Controlling -> Create and Change Controlling Scenario
Dhiraj,
I think you asked this same in controlling, so same answer: Note
1647563 - CProjects, acct assgmt mngr, settl.rule of WBS elem. changed
Niranjan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.