on 04-22-2014 8:28 PM
Hello All,
I entered a sender cost center, an activity type and a receiver cost center in KB21N and entered the quantity as 1. SAP makes the price show up as 1.11 CAD.
I maintained the price for this activity type and cost center as 1, why is it picking up 1.11 rather than 1 in KB21N?
My cost center's currency is CAD, there should be no exchange rate type that is affecting this right?
I checked CAD-USD in table tcurr just to make sure that no exchange rate was affecting this and I didn't find any exchange rate that would make it 1.11.
Please help
hi
Have you done any actual activity price calculation for the CC before doing KB21N. If yes that may be the actual activity price.
Regards
Rajneesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check OKEQN currency setting what Exchange rate type you maintained there.
also a lot of time SAP calculate M as exchange rate type check the value date also
Thanks
Hrusikesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.