PSV1 !!!

Former Member
0 Kudos

Hi All,

I have config T & E Management; while i have checked business event menu under attendance menu;

it shows check mark all the day off. Please let me know how to remove. Have attached screen shot.

Regards

DR

Accepted Solutions (0)

Answers (8)

Answers (8)

Former Member
0 Kudos

Hi Dibya,

In the main menu go to the training and event management, or use T-code LSO_PVMN:


after that when you want to define the course type you see the screen such as bellow:


and in the course type info you can set this parameter:


Regards,

Former Member
0 Kudos

Hi Dibya,


First of all you need to active the integration between Time Management and Training and Event Management.



in the next step set parameter such as bellow


After that when you define the course type in the "Course Type Info" tab do the setting about day off


Regards,

Shirin

Former Member
0 Kudos

Dear Shirin,

Am not able to find "Course Type Info" Tab; please guide me.

Regards

DR

Former Member
0 Kudos

Hi

Check the same in PP02 with IT-1029.

former_member193652
Active Contributor
0 Kudos

Hi Dibya,

Which version of SAP you are running?

Regards,

Omid

Former Member
0 Kudos

Hi Dibya,

This is due to your settings in the setting menu,


Regards,

Shirin

Former Member
0 Kudos

Hi Shirin,

Could share me the path.

Regards

DRanjan

Former Member
0 Kudos

Hi

Go to PP01 and give your specific BET and select the Infotype " Business Event Type Info " and change.

But this option is for Allowing employee to book an training course even if he is in Off.

i think your issue is for friday also it is showing as OFF DAY in the BE schedule

can you specify your exact issue please. 

Former Member
0 Kudos

Hi All,


Have checked the factory calendar,it's fetching factory calendar "IN"; however it's check mark mon-Fri.


whenever i have created "business event includes day off" still it's shown check mark under day off column.


is it possible i can customize as per my requirement; if i will create "business event". it shouldn't

check mark under day off column.

Have attached screen shot.


Regards

DR

former_member193652
Active Contributor
0 Kudos

Hi Dibya,

What is work schedule rule for this EE? Is s/he off in these 3 days based? I think 05.05.2014 is OFF(maybe public holiday in your calendar), isn't it?

What you would system do in this case? You would system does not allow to book a course for OFF days?

Regards,

Omid

Former Member
0 Kudos

Hi Dibya,

It's looking like standard screen that you don't get option to Hide this Field,

I can't able to check in due to lack of system, any way check the config once for any option may available.

All the best.

Former Member
0 Kudos

Hi ,

Checking based on the value in a field FREEDAY in table DAY_ATTRIBUTES

of function DAY_ATTRIBUTES_GET

please check factory calendar which relevant to your system - transaction SCAL

in my system factory calendar 01 - Germany (Standard)

Regards,

Boris.

Former Member
0 Kudos

Hi,

in you calender have you given Friday, Saturday and Sunday as off ?

Former Member
0 Kudos

Hi,

can you check through PSV2 may can change ?