on 04-23-2014 10:39 AM
Hi Friends,
While creating Work order based on priority system is assigning Basic start and finish dates,however while releasing the work order i want to copy these dates in to scheduled start and finish dates irrespective of operations.
how can we approach this requirement,could you please through some light.
Thanks & Regards,
Srinika
Scheduling will happen the scheduling configurations done in above mentioned configuration.
But, it will do the reverse to your requirement. Basic dates can / cannot be adjusted according to order / operation scheduled start date.
Scheduling is happening based on Control key at operation level, Operation Hours, Scheduling type which you mentioned.
Based on the scheduling type, scheduling will happen automatically either forward, backward, etc.,
I am not sure whether you can achieve this requirement using development.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Srinika
Have a look at the Scheduling Parameter settings in the IMG:
Plant Maintenance and Customer Service
-Maintenance and Service Processing
--Maintenance and Service Orders
---Scheduling
----Set Scheduling Parameters (transaction OPU7)
Look specifically at the Adjust Dates field.
PeteA
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
86 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.