Month End CO Planning , In T.code KP98 Copy Data to Plan run System pick Error message
"Primary Cost Element xxxxxxx is not supported in secondary Cost planning'"
Anybody face the same issue in your projects. Kindly guide me to solve this issue in Production
Regards
Dharmendar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Dharmendra,
As per KP98 you are copying Actual data to Plan period.... I hope your cost center actual data is having values only for the Primary cost elements... and no values to Secondary cost elements.... Right now for your Cost center there might be Some Secondary cost centers assigned to it... Please verify the secondary cost center master data in default account assignment tab and remove this Cost center... and rerun KP98...
Thanks
Surendra.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.