on 04-23-2014 1:38 PM
Hi,
We are running MRP through background job...after completion of MRP Run how to see the list of materials planned in that particular MRP Run...
plz help
Thanks
Kumar
Hi ,
If you goto BG job logs in SM37-Enter Job name or user name -Execute and then Hit the Spool and Mark the Spool chek box against the spool number generated after the job finished and click on detail ( magnifying glass)- Here you will get the list of materials for BG run of MRP.
Regards
JH