on 04-24-2014 9:13 AM
Hi Guys,
Can someone tell me whether I can run background Job to fill setup table of 2LIS_03_BX and 2LIS_03_BF at the same time?
By the way, whether I can run background job by different sever using different filters(site range A, B, C) to filling setup table of 2LIS_03_BX?
Thanks.
Regards,
Rojay
Hi,
filling setup tables for two data sources at a time no issues. But if you huge data and ecc server busy then that might may cause delay.
From menu options you may find background options.
First we need to fill BX data source later remaining data sources.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
OK, In fact, BX and BF data come from different tables(BX: MBEW BF:MSEG), maybe there are some other dependency when background Job running.
For another question, I will have a try to run different background job to fill BX setup table by filters(site range A, B, C) in two sever instances, and I think there will be no problems.
Thanks.
Ok, this is what I need, I can fill setup table of BX and BF in parallel in ECC, but I will load BX data into BW cube firstly, and then BF data. As well, I can also fill BX setup table by seperated background job in different instances by site range A,B,C.
All what I want to take steps is to reduce the server downtime.
Thanks.
Hi,
its all depend on ECC server load.
if your source system is always busy other loads then you need to schedule your background jobs on special application server with help of basis team.
if you know background job name, inform to basis team i think they can run your job on particular instance. For BX you can initial stock at time. for BF you can use possible selections. As per the data volume loads(setp table filling) may finish in time.
Other wise you can do this activity at weekend where there is no business.
Thanks
Thank you very much for suggestions!
In order to reduce one server workload(big volume data) and ECC server downtime, I must make a detailed plan to finish it. Wish myself success!
Thanks.
Hi Rojay,
1) There is no set up table concept for BX...
2) Set uptables are there for BF..
For inventory, its better to follow sequence as mentioned by Phani.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Rajesh,
All three data source have setup table concept.
LO extraction means you should fill the setup tables.
2LIS_03_BX (Stock Initialization for Inventory Management)
2LIS_03_BF (Goods Movements from Inventory Management)
2LIS_03_UM (Revaluations) - captures revaluation data.
please refer the below document for your reference.
Thanks,
Phani.
Hi Phani,
what i mean is in LBWE we cannot see BX... it will start with BF and UM.
you can start MCNB and BF set up tables in parallel as i donot see any risk but to be safe we follow the sequence and infact BX is not being used at all. We are from BF and UM..
.I should have explained more in the previous post.
Regards.
Rajesh
Hi,
Fallow the sequence of table while filling of set up table.
2LIS_03_BX
2LIS_03_BF
2LIS_03_UM
Thanks,
Phani.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
23 | |
11 | |
9 | |
8 | |
5 | |
5 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.