on 05-12-2014 9:53 AM
We are in a process of EHP 6 upgrade on WIN2008 and got stuck in the execution. We are getting the following message in SUM (10SP07):
Checks after phase MAIN_SWITCH/SUBMOD_SWITCH_OLDREL/SUBMOD_CRR_LAST_CHTRANS/RUN_CRR_LAST were negative!
The error we find in the logs is - No tasks exist for transition "LAST_TRANSFER" and scenario "ISU".
We have followd note 167856 which describes this issue, however we are not able to start and stop the transfer as mentioned inthe note.
In transaction crr_control the status is " The replication of recordedchanges is not enabled".
When we try to start the transfer wee see a message on the bottom of the screen "transfer of changes is not enabled". and In the log section there is the message "No tasks exist for transition LAST_TRANSFER and scenario ISU".
We tried stopping and starting the shadow instance and reexecuting the phase in SUM but it continues to fail.
HI Basis
Did you solved your problem?Could you help to share the solution?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
To restart the replication of recorded changes go to transaction CRR_CONTROL in the shadow system. I need to restart the process with user DDIC.
Select Control --> Start Transfer
This will trigger a batch job. The problem that I saw is that a previous run of this job had failed.
Again within CRR_CONTROL, select Contrl --> Stop Transfer. This will allow the batch job to finish successfully. I was then able to restart phase RUN_CRR_LAST and it finished successfully.
One other thing to consider here is that I was using SUM 1.0 SP11 rather than SP7.
Regards,
Mike Sharrar
Have you also checked SAP note 1678564 as Deepak suggested above? This note provides additional troubleshooting steps for nZDM.
http://service.sap.com/sap/support/notes/1678564
Regards,
Mike Sharrar
Hello Henco, Zhang and others,
did you try killing the corresponding job process? Please refer to note #2059084, which asks to kill the process (for another purpose, but it still valid). Then restart CRR_CONTROL.
Another know reason for the hanging/delay are the RSZ* tables, which belongs to BEx analyzer. They have a special delivery logic, which can take long processing when being copied online in nZDM procedure. Please use the very last version and patch level of SUM always.
Best regards,
Tomas Black
Hello Chandra,
ok, thank you. Please always use the very last patch level of SUM to ensure an optimized upgrade procedure.
As an additional information I suggest you to add the following lines to the file CRRTABLIST.LST , as they have caused some minor delays within CRR:
E SMIMCONT1
E SMIMLOIO
E SMIMLOIOT
E SMIMLOPR
E SMIMLORE
E SMIMLORI
E SMIMPHF
E SMIMPHHR
E SMIMPHIO
E SMIMPHPR
E SMIMPHRE
E SMIMPHRI
This will exclude them from CRR copy. You must fill this .LST file before starting the upgrade - or at least before starting phase MODFILE_CRRTABLIST.
Regards,
Tomas Black
Hi,
Does anybody have the solution for this?
Because the suggestion mentioned above doesn't help in my case.
thanks
Rohit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello all,
I had the same issue during my last upgrade, when I restarted the shadow instance I got below message:
After some digging in the system it found out that job RSUPG_ISU_CRR was cancelled due to the shadow instance stop/start, so the solution is to restart that job in SM37.
After CRR_CONTROL looked better :
I hope that it will help you !
best regards.
Karolina
Hi Basis,
Could you refer troubleshooting steps in SAP note
1678564 - Restrictions, Database-specific Settings, and Troubleshooting of nZDM for SUM
4.4. Phase RUN_CRR_LAST: No tasks exist for transition "LAST_TRANSFER" and scenario "ISU"
The above mentioned error message is displayed in log file RSCRRLST.ELG. To solve the issue, proceed as follows:
If above solution does not work , please raise an OSS under BC-UPG-DTM-TLA
Hope this helps.
Regards,
Deepak Kori
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Basis,
I feel that it is a problem with SUM1.0 SP07 .
As per SAP note 1678565 - Prerequisites, Terms and Conditions for nZDM/SUM
- Install an Enhancement Package on top of any ABAP system with a target release based on SAP NetWeaver 7.0 Enhancement Package 2, SP8 or higher, e.g. :
- Install SAP Enhancement Package 5 on a SAP ERP 6.0 system with SAP Enhancement Package 4
- Install SAP Enhancement Package 2 on SAP NetWeaver 7.0 (ABAP)
Can we check this with SP08 or higher patch of SUM.
Hope this helps.
Regards,
Deepak Kori
Hi,
I was facing the same problem in my upgrade to CRM 7.0 EHP3.
I also got the error message "transfer of changes is not enabled" in crr_control shortly after restarting my shadow instance and one step before the system downtime began.
The solution for me was to search in sm37 of the shadow instance for aborted jobs of user ddic.
I had two aborted jobs that had something to do with crr_contol.
After rescheduling the aborted jobs I was able to see the crr_control running again.
I didn't even have to restart the transfer.
Regards
Andi
User | Count |
---|---|
78 | |
9 | |
9 | |
7 | |
7 | |
6 | |
6 | |
5 | |
5 | |
5 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.