Hello Everyone,

I have configured a Release Procedure for contracts and Assigned the changeability release indicator to 4.

The requirement is configure the release procedure so that any changes in value, quantity, item text ... etc should trigger a new release.

How can I configure the system to meet the requirements, given that I have used the release indicators changeability fields 1 through 6 and still didn't meet the requirement?

Thanks & Best Regards,

Yousif.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

hi yousif ,

use changability factor 1, so it will not allow u to change contract after release and if u wanna change u have to unrlease the contract. b'coz no standard functionality exit for text change ,

i hope this will help u out , otherwise try for exit.

regards,

praful

Former Member
0 Kudos

> hi yousif ,

> use changability factor 1, so it will not allow u to

> change contract after release and if u wanna change u

> have to unrlease the contract. b'coz no standard

> functionality exit for text change ,

>

> i hope this will help u out , otherwise try for

> exit.

>

> regards,

> praful

Thanks Everyone for the quick response,

Let us consider I used the Customer Exit, what exit should handle this scenario?

Thanks.

Yousif.

Former Member
0 Kudos

hi ,

u will have to find out which exit will meet ur reqirement use t-code SMOD and iin F4, put ME as package for PO , it will show u all the exits available for the me21n

regards,

praful

Ramki
Active Contributor
0 Kudos

Hi Yousif

M06E0004, M06E0005 and M06E0008 are relevant.

But, I doubt whether they would be useful to you here.

Best regards

Ramki

Ramki
Active Contributor
0 Kudos

Hi Yousif

Use 'not changeable' indicator. This means, you need to cancel the release befoe making any changes. Then any changes would trigger the release procedure again.

Best regards

Ramki

dhrubacharan_behera
Active Contributor
0 Kudos

Hi Yousif,

If you have created a characteristic as "total Contract Value"giving communication structure CEKKO - field GNETW in additional data tab it will take care of resetting the release in case of change (only increase in value) in value or quantity which ultimately is related to value.But I am afraid change in texts are not generally taken care of for changing release.