"Restore" Work Force Planning after status change TECO->REL??

former_member1139057
Participant
0 Kudos


Hi'

When status TECO is set the Work Force Planning is deleted.

Here:
SAP PS FAQ - Product Lifecycle Management - SCN Wiki

they inform that CMP9 should be able to "recreate" the WFP-data.

Can anyone help me how to do this?

Best regards

Lone

Accepted Solutions (1)

Accepted Solutions (1)

former_member1139057
Participant
0 Kudos

Hi'

I have raised an OSS-message for this issue.

The answer is that the documentation is wrong.

It is not possible to "recreate" WFP by changing the status back to REL from TECO.

They have advised some customers to create a user status TECO, with same "transaction control" as system status TECO. In that case the WFP is not deleted.

But - the documentation should now be opdated and reflect the standard behavior.

Regards

Lone

Answers (1)

Answers (1)

former_member195427
Active Contributor
0 Kudos

Hi,

Yes, its true . Resetting TECO to REL followed by CMP9 will regenerate capacity evaluation.

This holds true not only for workforce planning but also for material requirements generated for projects.

In case of materials we need to regenerate requirements using program RLORD035.

What is the issue with that, please specify.

Regards

Saurabh

former_member1139057
Participant
0 Kudos

Hi'

Thank you for answer. Which data do I have to use as input in CMP9 at which tab page?

I have removed TECO - status now REL.

I goto transaction CMP9 - Enter Project-ID at Tab-Page "Project selection".

Settings: Here I have a Profile (Week -2 to 20 weeks)

I use F8

But I do not see the deleted Work Force Planning informations?!

Could it be differencies in customizing?

Best regards

Lone

Former Member
0 Kudos

Try to change the planning period start and finish dates manually after you enter the Profile and execute.

Maybe you could check CMP2 once you are done with CMP9. Let us know if it works.

former_member1139057
Participant
0 Kudos

Hi again

Thank you for input

I have tried to change the period in CMP9. I have tried both with activites with WFP - but without Confirmation - and with conformation.

I have checked CMP2 - no WFP data

Any other suggestions? It would really be nice for us if we can get the WFP-data back

Which tables shold the data be in when TECO is set? As far as I remember the data is in tables KBED/KBEZ/KPER but are deleted from these tables when TECO is set.

Regards

Lone

former_member195427
Active Contributor
0 Kudos

Hi,

Try CJEN followed by CMP9 again. Also, make sure all the necessary check boxes are marked for  workforce planning profile(Ctrl+F5).

Regards

Saurabh

former_member1139057
Participant
0 Kudos

Hi'

I have tried CJEN - no changes.

Which check boxes influenze at this functionality? All check boxes seems to be marked.

We are at SAP ECC 6.0 - SAP_APPL 606 0007 SAPKH60607

It woul really be great if we can make this work!

Regards

Lone

former_member1139057
Participant
0 Kudos

Hi'

I cannot make this work - I hope you can help me to make it work!

Regards

Lone

former_member195427
Active Contributor
0 Kudos

Hi Lone,

I am not sure..  May be you can raise an OSS to SAP for it...and let us know the outcome of it.


Thanks.