I have a maintenance plan with scheduling period 365 days and call horizon of 0% the call has been started on 07/09/2010 the work order created during the call has been completed and set to TECO but upon checking now the next status are on hold? we want to schedule this to automatically create a work order after setting the previously order to TECO.

thanks and God bless

Accepted Solutions (0)

Answers (2)

Answers (2)

sebastian_lenartowicz
Active Contributor
0 Kudos

Greetings Peach,

When you go into transaction IP10, does the next call have the status "Hold" or "Save to call"? Can you post some screenshots?

Also, check in t-code SM37 whether there is a periodic batch job running for you for the ABAP program RISTRA20

If not, you will have to schedule on, go to t-code IP30, input your various selection criteria for the Maitnenance Plans that you want to generate Orders for, such as:

Maintenance Plan category

Maintenance Plan sort field

Maintenance Strategy

then "Execute in background" and schedule it for a particular time (typically outside of working hours at night) and with the "Periodic job"  flag.

Former Member
0 Kudos

How you are running scheduling?? IP10 or IP30??

Run daily batch program for Order scheduling in IP30. There are many threads & documents available for setting Background Job.

Immediately after TECO of Preceding order will not generate any Subsequent orders. It should be done via IP10 / IP30 scheduling only.

Former Member
0 Kudos

iP10

Former Member
0 Kudos

Run it in IP30, it will create the Order.

Attach the below mentioned screen shots.

  • Maintenance Plan Cycle tab of Maintenance Plan
  • Maintenance Plan Scheduling Parameters tab of Maintenance Plan
  • IP10 of that Maintenance Plan