on 07-11-2014 2:05 AM
I have a maintenance plan with scheduling period 365 days and call horizon of 0% the call has been started on 07/09/2010 the work order created during the call has been completed and set to TECO but upon checking now the next status are on hold? we want to schedule this to automatically create a work order after setting the previously order to TECO.
thanks and God bless
Greetings Peach,
When you go into transaction IP10, does the next call have the status "Hold" or "Save to call"? Can you post some screenshots?
Also, check in t-code SM37 whether there is a periodic batch job running for you for the ABAP program RISTRA20
If not, you will have to schedule on, go to t-code IP30, input your various selection criteria for the Maitnenance Plans that you want to generate Orders for, such as:
Maintenance Plan category
Maintenance Plan sort field
Maintenance Strategy
then "Execute in background" and schedule it for a particular time (typically outside of working hours at night) and with the "Periodic job" flag.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
How you are running scheduling?? IP10 or IP30??
Run daily batch program for Order scheduling in IP30. There are many threads & documents available for setting Background Job.
Immediately after TECO of Preceding order will not generate any Subsequent orders. It should be done via IP10 / IP30 scheduling only.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.