Alternative to Intra company STO

Former Member
0 Kudos

Hi ,

We have two plants in Pune in India, need to move the stock from SUP1( supplying plant) to REP1( Receiving plant). Actually we can do this in Intra Company STO. But currently there is no STO setup ready in the SAP system. As of now only Trading process set up is available in SAP system.( receiving the goods from China and selling it to Indian customers).

As per the business requirement they want move the stock from SUP1 to REP1 immediately, Business can’t wait until the STO set up is moved production.

Do you advise any other alternative solution for work around apart from Intra company STO process?

Thanks,

1 ACCEPTED SOLUTION

binoy_vargis1
Active Contributor
0 Kudos

Hi,

Do Transfer posting in MB1B in 301 movement type. Adjust the Excise in both the plants by making use of J1IH(Manual Excise JV).

Regards

Binoy

5 REPLIES 5

Former Member
0 Kudos

have you checked transfer posting from plant to plant

binoy_vargis1
Active Contributor
0 Kudos

Hi,

Do Transfer posting in MB1B in 301 movement type. Adjust the Excise in both the plants by making use of J1IH(Manual Excise JV).

Regards

Binoy

Former Member
0 Kudos

Thanks for both of you. Let me try this and will also check with MM team.

0 Kudos

Hi Surya,

Let the community know how you solved it. This will help somebody searching with a similar query.

Regards

Binoy

Former Member
0 Kudos

Hi All,

Thanks all for your reply. Currently business has agreed until the STO configuration move to Production. Hence i could net test the above soltuion, however it seems to be relavant solution.

Thanks,