Hello guys,

I cannot get system to create a project from strandard structure (standard wbs + standard network + standard milestone).

The reason for it that I get error

CJ565 - MRP controller &2 does not exist in plant &1


So the question is  - where exactly the default mrp controller is stored for standard network?


Thanks.

Regards,

Laimonas

Accepted Solutions (0)

Answers (3)

Answers (3)

sanjeevc
Active Contributor
0 Kudos

Hi,

just create a MRP controller in OMD0 transaction with the combination of Plant.

then create a project system will allow. because without MRP controller network creation would not be allow by system.

if your network profile is not containing MRP controller then you can put it manually when system ask while creating a project.

Regards,
Sanjeev

laimonas_bindokaitis3
Participant
0 Kudos

Danger is cleared.

It was the standard WBS who did all the mess (to be specific, it was project profile in std.project definition). It had a wrong plant there.

Error description was too abstract to identify the problem at a glance.

Thanks everybody.

0 Kudos

Hi

please check network profile as in screen (tr OPUU)

(st network has already a profile and this profile carries the mrp contr)

Hope it helps

Panagiotis

laimonas_bindokaitis3
Participant
0 Kudos

I checked this. MRP controller and plant combination is maintained properly. But the error persists.