i am getting negative planned values in CJ40 against Order/Network column. I am unable to find the root of this value.
Here i am using the network costing, BOM's and MRP run process. So can any one tell me how to find the root of that negative cost plan value.
Reagrds,
Rao.
Hi Rao,
Could you please perform the below steps?
1. Execute the transaction CJEN for the affected project
2. Execute the report BPDIST0 in SE38 for the affected project
Should the problem still persists, please implement the report ZAIMPLDL
from the attached note 887864.
1. Execute the report ZAIMPLDL for the project
2. Then execute CJEN and BPDIST0 again.
Regards,
Enrique
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Rao,
Pls brief your query , were u find negative planned value n all.
so that we can understand your issue to provide solution.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.