HI, experts
RT, could we realize the transferring PR from ECC to SRM without PI in SRM version 7.x? , if can, how to do ?
thanks
Jesse.
Hi Jesse,
PR and PO both can be transferred to the SAP ECC backend through RFC and hence PI is not necessary. It is only if you need SRM to connect to non-SAP systems (& SAP systems like SUS), you require PI.
Please set-up an RFC connection in SM59, job(as mentioned by Robin) and the other settings like n umber ranges, transaction types and back-end document types you should be good to go.
Hope this helps
Cheers,
Yateesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Sure,
just follow the steps in the config guides. Schedule BBP_EXTREQ_TRANSFER and you are set.
Regards,
Robin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.