on 07-23-2014 12:44 PM
Hi,
We have done month end closing process for Production Orders which included WIP Calculation & Settlement. However for few production orders whose status was DLV, WIP got calculated again along with Price Difference accounting entry. Hence its showing 2 entries one for WIP & another for Price Difference which is incorrect. System should not calculate WIP for the orders having Status "DLV".
Please suggest at the earliest as the month end closing activities are held up due to this issue.
Regards,
Varsha
If this is still an issue, please post screen shots of the GL postings from each settlement, include the dates; What is your month end date and what date was the DLV status set.
Regards
Althea
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Varsha
If for the orders WIP calculated and settled earlier, and again at the time when the status is DLV, WIP calculation is run, system calculates the amount of WIP amount to be posted for the reversal of earlier posted WIP and at the same time variance is also calculated for variance settlement. This is standard behavior.
So what is your expectation please share.
Rajneesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.