on 07-23-2014 4:47 PM
Hello,
I have created this post because I have an issue regarding sheduling date for FG (finished good) and SFG (semi finished good) after MRP run.
We are in Make to stock scenario (plannig strategy 40)
Of couse, SFG is linked to FG in BOM.
We use lead time schedling for MRP run. So we use data from routing
After MRP run the result is as follows:
=> Date for FG (finished good) in planned order :
Order finish date: 02.09.2014
Order start date: 02.09.2014
Scheduled finish date: 02.09.2014 (16:15:00)
Scheduled start date: 02.09.2014 (14:30:56)
Scheduling operation time: 1.5 hour
For finished good no problem !
=> Date for SFG (semi finish good) in planned order
Order finish date: 02.09.2014
Order start date: 02.09.2014
Scheduled finish date: 02.09.2014 (16:15:00)
Scheduled start date: 02.09.2014 (13:56:15)
In the example above, the scheduled finished date for for SFG is the same than FG (16:15:00). The SFG is manufcture in the same time than the FG. For me, the SFG should be produce before the FG, so the Scheduled finish date should be equal to the Scheduled start date of FG.
The sheduled finished date for SFG should be 14:30:56 and the scheduled start date 2 hours before (backward ascheduling). Operation time for FSG.
Could you tell if it's a normal behabiour of system, or if a setting is missing somewhere ?
Thanks in advance for your help
Best regards
Corentin...
Corentin,
Your SFG order Finish date would be your FGs order Start date if you have created requirement which needs more than one day time.
And as far as times concerned for both materials orders would be created on same time even though WC is overloaded if you are using same WC, as finite scheduling needs to be done manually in R/3 this is standard behavior of system.
Br
KK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Thanks for your help, but I have still an issue about it!
When I convert planned order to production order, I have the same probleme. SFG (Semi finished good) is manufcatured in the same time than FG (finished good).
Find an example below:
How ensure the availability of SFG (Semi finished good) before the scheduled start date of FG (finished good). Have I to use Margin Key for that, by using a float after production for SFG. For me SFG have to be manufactured before FG;
Thanks a lot for your help
Corentin,
Did you read my earlier reply?
Your SFG order Finish date would be your FGs order Start date if you have created requirement which needs more than one day time.
And as far as times concerned for both materials orders would be created on same time even though WC is overloaded if you are using same WC, as finite scheduling needs to be done manually in R/3 this is standard behavior of system
Br
KK
Hello Kiran,
Yes, I have read you reply. But there is something I don t understand. Even if for SFG I need more than one day of processing time, as you said in your post. The order finish date for SFG is the same than Order finish date for FG. The SFG is not manufactured before FG. For that, I need to apply a fload after production for SFG to ensure the availibilty. Is it an other solution ?
Both material are produced on different Work Center, and they are not overloaded. So I don t need to level the load.
Thanks for your exmplanation.
Best regards
order
Hi Kiran,
I was not enough clear in my last post. I agree with you that the SFG order finish date is the FG start date. My issue is about the time of FG and SFG. The SFG order end on the 26.08.2014 at 16:15 PM Like the FG. The FG order start time should be scheduled after 16:15, after SFG complétion, and not at 14:30. I guess finite scheduling is required?
Thanks for your confirmation.
best regards
Corentin,
Both material are produced on different Work Center
As you had mentioned in your previous reply both FG and SFG are produced on different WCs then why you are interrelating these both orders?
The FG order start time should be scheduled after 16:15, after SFG completion, and not at 14:30.
As both are different WCs we need to validate already occupied load on these WCs for your given times.
Br
KK
Corentin,
Can you Share your MD04 snap shots for both FG and SFG?
There should be some exception message - 10 for Rescheduling in?
Br
KK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.