PM maintenance plan.

0 Kudos

Hi PM Experts,

We've customizing the maintenance plan wihch have the plan defined as 150H  and 600H in the IP10 defined for this maintenance plan,

and the  mensure document is 144H for all of then, and if we run the IP30 the system is created another PM oder even the Hours is less the 150 as is defined in the plan.

Could you please help how to solve this issue?

Usually if the plan os defined for 150H when I run the IP30 should not created another PM Order.

Best regards

Rogerio

Plant maintenance

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos
  • What is the Call Horizon maintained in Maintenance Plan
  • What is the Interval for Call Object maintained while running Scheduling in IP30
  • What is the Annual Estimate maintained in Measuring Point

Highlight the row in IP10 which has created the Call Object, click on "Calculator" button in the bottom. It may give some idea about the call object creation details.