After creating Bom,Routing,workcenter and production version for the material.

If user delete all child componenets for a header even though error msg displayed, system is allowing to release and

save the production order.

Please let me know how to restrict production order creation if bom compoenets not available.

Thanks in advance.


Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Very first you need to check BOM and Routings validity dates then the date on which you are creating your production order.

If above parameters and settings are ok then for your business process where BOM components are changed or deleted by users, you need to implement engineering change management as well as restrict users through authorization for the master data change transactions. If this is to be done then in production order always system will capture/show the valid and approved master data.

Now in next step, that is production order creation, here many time users do changes like deletion of BOM components and production operations etc. This can be restricted by several ways which you can find in previous SCN discussions related on same topics. Refer below thread for as such discussions on SCN,

You can refer below thread to create the transaction and screen variant in SAP,

Regards,

Narresh

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi

Make sure that there is at least one item with the flag 'production relevant' flagged.

BR

Caetano

Former Member
0 Kudos

Hi,

This error came from the valid dates of routing and BOM. Pl ensure the  Valid from Dates againist the production order dates.

We can control the production orders creation if the components are non avaliability ( missing parts) through confg of order control (OPJK) .

Choose the collect conversion filed and keep it 3 in that filed.

Regards,

Sivaprasad  

ilavarasan_td
Participant
0 Kudos

Even though i have maintained the value as you said still production order is allowed to save.

Please refer the below screen shot.

former_member184574
Active Contributor
0 Kudos

Hi ILAVARASAN,

are you creating production order manually through CO01 or converting planned order to Production order ???...maintaining 3 in collect conversion field only works during mass conversion of planned orders to production orders through CO41..

for manual creation of production order and single planned order conversion to Production order through MD04 even though materials are not available system will allow you to create Production Orders even though maintain 3..check the below thread..

Thanks