Hi all,
We enter KMAT and configuration values in SD order.
In order to have our BOM exploded according to configuration in Production order, we need to go CU51 and save the configuration.
The question is, CU51 is really necessary for activating configuration ? Because we never change anything in the BOM over CU51, which is to explode according to Sales order item characterictic values. I wish, the BOM explodes in production order appropriately without visiting CU51
Thanks
It is not mandetory to go to CU51 for each sales order item. CU51 can be use to change any characteristics value in WIP material after sales order release for pricing and production. sometimes this transection can be use to reexplode BOM after charcateristics value changes in WIP materials.
To ensure BOM explosion "Engineering" button needs to be press in VA01 / VA02 transection.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In order to ensure that an order BOM is exploded, one of the following steps must be performed:
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
10 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.