Hello,
When running MD04, forecast (VSF) and planned orders are landing on the same day. This is causing confusion for the users. Is there a setting that's causing this to happen? We are using checking rule PP. Should we be using A instead? The planned order should actually be showing up before the forecast because we don't want the inventory to show negative from the forecast. Any help will be appreciated.
Thank you.
MZ
Hi MZ,
You can maintain the Safety time/act.cov. field in the Material Master MRP2 view.
Safety time (in workdays)
If you define a safety time, the requirements in MRP are brought
forward on the time axis by the number of workdays you define here.
So try to enter 1 day and you will see that the MRP will create the planned orders starting 1 day before the VSF.
Kind Regards,
Mariano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi MZ
On the standard MRP process, the planned order basic finish date will generally match the requirement date.
Check this document which explains the scheduling in more detail:
Backward Scheduling for In-House Production - Material Requirements Planning (PP-MRP) - SAP Library
BR
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.