Hi experts,

I've a question regarding downtime scheduling in Solman Technical Monitoring.

I have a system in which I've maintained 24h workmode (productive HA system).

So the system has a mode from 00:00 to 23:59.

But how can I now schedule a downtime for the same day in IT-Calender?

e.g. on Monday 08:00 I would like to schedule a downtime for Monday 09:00 to 11:00.

I always get an error message, that there is already a workmode active.

I only can schedule a downtime for coming workmodes, so earliest by Tuesday 00:00+.

Kind regards

Accepted Solutions (1)

Accepted Solutions (1)

divyanshu_srivastava3
Active Contributor
0 Kudos
Private_Member_19084
Active Contributor
0 Kudos

thank you

Answers (0)