Dear All,
Please Guide me for that serious issue in capital project .
I have created a separate material Type for Capital project due to hit some specific g/l .
But in S_alr_87013558 ,it is showing only budget amount but not actual & commitment although there so many PR ,PO & goods issue ETC.
Please guide me ,what is the configuration requirement for that.
Thanks & Regards
Sambit
Dear All ,
According to your advice , i have checked .According to Mr. sampath , (cost element category should be 90 ) is working for service PR & PO but in case of Material PO & PR ,GRN .actual & commitment is not coming .(There is so many po,grn for machines)
Please help me for That
Regards
Sambit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I think most of the previous posts mentions everything you need to check/do to get your report up and working.
Lastly also check for relevant authorizations. I have faced this issue many times and it turned out to be because of missing authorizations.
Thanks
Saurabh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
There are lots of customize setting to not updating commitment, so you have to check below point:
Check OPSV setting and maintenance order as 30 should be tick mark then check commitment report surely commitment will come under report.
Check in COSP table if you have commitment value, with value type 21 wbs you can find it in PRPS table & check in COOI table , ME5J Reorts/ and S_ALR_87013558 reports, whether Commitment has captured.
check below link also
http://help.sap.com/saphelp_47x200/helpdata/en/4c/22756546e611d189470000e829fbbd/frameset.htm
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In addition to the suggestions above, check your value category customizing. Hopefully you might the cause of the issue.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Get G/L of material from OBYC settings of MM ( material master valuation lass ->OBYC->GBB(I think) ->G/L )
Pick this G/L and check its type in FS00 ( B/S or P&L). If its a B/S item then create Cost element for it (category 90)
If its maintained as P&L a/c then check whether any 'Default account assignment' is made for corresponding CE in OKB9 ( a cost center).
Let us know with your findings.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
What is your component process? Is it through CJ20N or not. if not it will not show up. is this problem for one component or else every component.
Does planning profile activated for commitments?. check OPSB.
Thanks,
Sudhakar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI,
Report "S_alr_87013558 " is based on table RPSCO. please check whether data exist in this table or not. you can also check report "S_ALR_87013557 - Budget/Actual/Variance"? have you created PR and PO for project with account assignment 'Q'
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.