on 07-28-2014 2:54 PM
Hi guru,
I created a project with several activities. I created WBS BOM with two materials tIhat need to be procured in advance.
I assigned FG to a network activity and the two raw materials to another ativity.
Now, if I run MRP, I have double dependent requirements about raw materials, more exactly one derived from FG and another one derivad from assignment to activity, In which way I can avoid this double requirements? I have to assign materials to activity because I need to use as requirement date, the activity date
Thanks
Regards
Raffaele
HI,
why you putting ROH material separately in network activity although you have already added FG material in network activity?
FG having BOM it self so far, then after MRP executing system will create PR for ROH and plan order for SFG/FG material.
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
please assign FG
do not assign any raw materials again to the activity
run the MRP
note that when MRP is executed,in the background ,as you have maintained the settings for materials,(consult with your MM consultant and PP consultant.),PR shall be created for the materials for which there is no project stock.and it shall also consider the lead time as maintained in the materials.
hope this shall help you
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Raffaele,
Can you please assign FG material quantity with -ve value and check your MRP run whether it still generates double requirement. Please check and let me know.
Thanks.
Saurabh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Raffaele
As per my knowledge u don't want to create PR for that Raw material which u assign to activity for Requirement Date, if yes then why u not change Procurement Indicator from PR+ Reservation to Reservation Only . This will not creates PR & u get the field for Requirement date also in Genral Data Tab of material
Thanks ,
Virendra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.