Dear All,

WE are trying to do progress analysis to calculate BCWP and BCWS for this we are using budget as a base. we are not getting any BCWP and BCWS values where as all other values like POC agg. Non Agg. are coming properly. Kindly suggest.

We have maintained following things.

For Activity we are maintaining Plan method as Time proportion and actual as Work.

For WBs we are maintaining Plan method as well as actual as 0-100 method

and after that we are confirming activity and executing CNE1 and after that CNE5.

Regards

Dheerendra Patil

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Dear Dheerendra / Shivali,

please check the following things

  • check that your objects have EV methods and progress version assigned
  • EV Setup
  • Link the EV Cost element to the cost element used on the project plan in spro under the progress analysis tab

Regards

PP

Former Member
0 Kudos

Hi Amit,

According to your reply I have checked the report"CHECKREPORT_PROGRESSANALYSIS"  and there it doesnot show any error.Also I have used budget overall as my base for earned value analysis.I have already gone through the links suggested by you and I fail to  get the desired solution.


Regards,

Dheerendra

Former Member
0 Kudos

Hi,

Then Wait for others experts comment on this.

Regards,

Amit

Former Member
0 Kudos

Dear Dheerendra / Shivali,

please also maintain the POC Weight and Schedule the project.

Regards

PP

Former Member
0 Kudos

Hi,

I think almost similar question already appeared in SCN and infact I replied to that question too.

please refer my thread.

You may also go through following threads.

Regards,

Amit Rajoria