I am new to PM module, we use Diamond die for drawing Al wires. We GI the material to Shopfloor by 201 movement and after that there is no tracking of the die.
Now the management want to track the spare life of the die and at the same time they dont want to have the stock in SAP as they are currently doing. How to monitor the Spare life without stock is this possible , pls guide me. I dont want to do it in enhancement (abap).
Arjunan,
At any point of time you will be able to get from IE02 tcode the report of Usage Period, giving you the details of the journey so far.
This is from my side. Wish better ideas flow for your issue.
Best of luck
KJogeswaraRao
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You could also serialise the material so that you can use the Serial Number functionality in SAP.
This will enable you to track the individual diamond dies.
Measurement points as described above will enhance the tracking of data.
PeteA
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Further to Jogeswararao's, I would like to include some more information,
If die usage is required basing on usage(no of times)then create measuring point for that created equipment and document it on usage,then you can track usage period and as well as no of usage times too.
Regards,
Nikhil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.