Hi,
When I create billing document for a service order according to the SO directly the accounting document can't generated. The error is as follows:
In Profitability Analysis (CO-PA), the system tried to valuate a line
item using the current standard cost estimate.
In order to determine the current plan period, the system needs to read
the valuation segment of the material master.
The system has found that the current plan period is not filled
for product "XXX" in plant "1100".
Display material (View: Costing)
The system looked for the material cost estimate using costing key
"001", as defined in the Customizing settings for CO-PA.
Anyone who can help me about this?
Thank you!
Regards,
Bamboo
Hi Bamboo,
Did the suggested link and note helped to solve your issue? If so, could you please close this thread and update the status of the question? Otherwise, please let us know the current situation.
BR,
Enrique
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Bamboo,
To avoid this error you have to change your KEPC setting in such a way that costing key YB2 is not
found. Else please refer to the WIKI page below which will help you avoiding the error:
http://wiki.scn.sap.com/wiki/x/WYANDw
BR,
Enrique
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check the following note:-
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.