Valuation with material cost estimate: error with product XXX error message KE350

Former Member
0 Kudos

Hi,

When I create billing document for a service order according to the SO directly  the accounting document can't generated. The error is as follows:

In Profitability Analysis (CO-PA), the system tried to valuate a line

item using the current standard cost estimate.

In order to determine the current plan period, the system needs to read

the valuation segment of the material master.

The system has found that the current plan period is not filled

for product "XXX" in plant "1100".

Display material (View: Costing)

The system looked for the material cost estimate using costing key

"001", as defined in the Customizing settings for CO-PA.

Anyone who can help me about this? 

Thank you!

Regards,

Bamboo

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Bamboo,

Did the suggested link and note helped to solve your issue? If so, could you please close this thread and update the status of the question? Otherwise, please let us know the current situation.

BR,

Enrique

Former Member
0 Kudos

Hi Bamboo,

To avoid this error you have to change your KEPC setting in such a way that costing key YB2 is not
found. Else please refer to the WIKI page below which will help you avoiding the error:

http://wiki.scn.sap.com/wiki/x/WYANDw

BR,

Enrique

Lakshmipathi
Active Contributor
0 Kudos

Check the following note:-

  • Note 2038550 - Error with material cost estimate in CO-PA valuation after upgrade

G. Lakshmipathi