Hello,

I wonder if there is a customizing setting or user exit/BAdI to have the Rescheduling date (MRP Exception message 10) in MD04 based on the date of the Schedule line with the confirmed quantity. Note we do not want to fix the quantity and dates (no ticking of VBAP-FIXMG).

Let me explain:

Sales order has a Schedule line with requested (First) date of 30.07 and confirmed quantity of 0 PC, and a Schedule line with confirmed date and quantity of 1 PC on 02.08.

We have a PO for the Material with Delivery date 04.08.

Now in MD04, for the PO, the MRP Exception message 10 says Rescheduling date = 30.07.

Is there a way we can have this Rescheduling date be in this case 02.08, being the date of the confirmed quantity in the sales order?

All this, without fixing quanities and dates.

Thanks in advance for any clues.

Kind regards,

Bart

Accepted Solutions (1)

Accepted Solutions (1)

Lakshmipathi
Active Contributor
0 Kudos

This is not SD related query but related to PP.  Anyway, have a look at this thread whether it is helpful for you

Else, I will move this thread to PP forum.

G. Lakshmipathi

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Bart,

i think that the rescheduling date of the P.O. has no relation with your sales order schedule line date.

Best regards.