Hi Experts,
I am having problem with budget exceeded error.
Scenario - When trying to invoice the P.O it prompt budget exceeded error but budget was available when checked the S_ALR_ report.
As it was very urgent, Budget was supplemented to pass the Invoice for P.O and after it is invoiced I could still see the budget available more than already available budget.
Example.
Invoice for Commitment PO - 200000
Budget Available - 50000
Supplemented Budget by 20K to pass on the Invoice as it thrown error while invoicing, Hence New Budget available after supplement is - 70000
After the invoice of PO - 200000
Budget report showed the same available amount as 70000 ( No Change in the original value of budget even after supplement of 20K)
so now I tried to reduce the budget back to 20k and roll back the budget back to 50K but system throws me the error as attached here.
I have tried to analyze the report such as CJI3, CJI5, CJ31 also executed RKANBU01, CJBN, CJEN.
This is done on lower level WBS and I have checked all P.Os and tax charged towards it to see if the available budget has been consumed with the tax amount or not.
Real values on the scenario are given below. I am not able to get the point on where the 4641.43 USD is budget exceeding
USD | 930451 | commitment |
345550 | actual | |
1276001 | total Budget Consumed | |
1289263 | Current budget | |
13263 | available |
Appreciate experts help and comments.
Thanks every one for looking into the post and tried to help on the started discussion.
The issue is resolved and I have analysed the cause of it.
Solution : Currency in availability control is maintained in USD & hence System issued error message in USD with Value and the exchange rates used to translate the currency was the first day of the year which cause the difference and budget exceeded.
Also refer note 906975 for good understanding and explanation on Currency translation in planning and budgeting
Hope this will help others at some point.
Cheers !
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Any advise from Experts is much appreciated !
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI
Step1:
Just check whether you have maintained person responsible
It is required that person responsible is maintained for WBS elements
Step2:
check the released budget and the year of release and the posting in which you are carrying out the ,is there budget available
this might help you to resolve your issue
Message was edited by: Sushrut Sheth
One thing is clear that system is checking budget of WBS in subject and giving error of budget against it. Just a workaround, instead of reducing budget by 20 K , reduce it by ( 20K- 4631.43) USD and check.
Or
Deactivate AVAC->Reduce budget by 20K-> Save ->reactivate AVAC->create new commitment (PR/PO) -> What is the new budget exceeded amount,Note it-> Supplement the budget by this value and check PR/PO again.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Saurabh,
I was not able to perform the steps you said as I don't ve controls to deactivate the availability control as its restricted.
Instead budget was supplemented for the wbs as needed for project and I was able to reduce the budget for 20k now but when I try to return back the budget from the available amount system issues me with error as attached.
When the wbs is budgeted in AUD and transacted in AUD Currency why the system issues messages with the value in USD, Is this standard behavior ?
I used CJ38 and get the same error as attached.
I have also checked if in CJI5 and for all the P.Os if its has tax amount which consumes the budget but still I am not able to figure it out.
This has been budgeted in AUD Currency and have USD as CO Currency.
I have checked the Exchange Rates in OB08 and still didn't get the difference in amount which should prompts exceeded budget message as plenty of budget available.
Not sure if budget translation from AUD to USD is happening correct.
Let me know your suggestions.
Thanks all for your comments.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
After doing the budgeting.. Do you also releases the budget ? If yes, then provide screen shot of CJ32 as well.
I have a doubt. I think you are releasing the header level WBS and keep child level WBS intact.
Provide the screen shot of S_ALR_87013558 and that too specific with that particular WBS which are creating problem for you. (Plz drag it to the right. I want to see the available, assigned amount).
Regards,
Amit
Hi Amit,
We don't have release functionality maintained for budgeting.
This is for child level wbs and sufficient budget is available.
As requested I have attached the screen shot.
Standard Report shows the budget in USD
And CJ31 also displays the budget in USD
I have also attached screen shot of budget in AUD, Where in on the available budget amount I am trying to reduce it by 20K in CJ38 which pops the budget exceeded error message.
Thanks
Hi Aoron,
Please try returning the available amount 13263 USD using cj38 if you wish to roll back to the original budget.
Regards
Varun
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I used CJ38 and get the same error as attached.
I have also checked if in CJI5 and for all the P.Os if its has tax amount which consumes the budget but still I am not able to figure it out.
This has been budgeted in AUD Currency and have USD as CO Currency.
I have checked the Exchange Rates in OB08 and still didn't get the difference in amount which should prompts exceeded budget message as plenty of budget available.
Not sure if budget translation from AUD to USD is happening correct.
Let me know your suggestions.
Thanks all for your comments.
Hi,
you are trying to reduce the budget from CJ37 ??? where you are now getting this error ?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.