Requirement in regards with MRP

Former Member
0 Kudos

Hi,

One of our clients has the following requirement -

MRP will be done based on MOQ (Minimum Order Quantity) i.e. SAP will consider, while MRP, that if an item is repeated 20 times, with qty sum = 43 nos, and its MOQ is 10 nos, then PRN (Purchase Requisition Note) 50 nos will be released.

The client is using SAP 2007 SP01 PL09 and he is ready to upgrade the SAP version to the latest.

I believe that this can be possible, so please let me know, in which version of SAP, is this possible ?

Accepted Solutions (0)

Answers (1)

Answers (1)

kothandaraman_nagarajan
Active Contributor
0 Kudos

Hi,

Please refer SAP note for solution:

862814
- MRP and lead time requirements

Thanks & Regards,

Nagarajan

Former Member
0 Kudos

Hi,

I don't have user id & passwd for SAP Service Marketplace

Regards,

Nikhil

kothandaraman_nagarajan
Active Contributor
0 Kudos

Hi,

Sorry.Not possible to paste complete SAP note here.

Thanks & Regards,

Nagarajan