on 07-31-2014 3:53 PM
Hi All,
I have the following problem in the CTM application. I have one location with a customer order and a firmed planned order. The firmed planned order has a goods recipe date one month later than the goods issue date of the sales order. When I run the CTM another planned order is created at the goods issue date of the sales order. I expected that the firmed planned order has been taken by CTM to fulfill the demand.
If have therefore allowed the late demand fulfillment for 100 days and set the strategy to the domino strategy.
Has anybody an idea what parameter I have to set.
Best Regards
Dieter
Hello Dieter,
What is the Late Demand fulfillment strategy you have selected in the CTM profile .
Regards,
Nick
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Dieter,
Please check if the plan order is tied to your SO (t.code /SAPAPO/CTMVIEWER or in the /SAPAPO/RRP3). Also check in CTM profile (tab Supplies) what is your settings in the supply control section (Build Up Safety Stock and Stock is available). They should be active.
In the Planning Strategy tab what is the scheduling direction and pegging type?
Also check the Planning Strategy (planning mode & delete mode).
Thanks, Marius
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.